] [Hide Context] IN THE SUPREME COURT OF BELIZE, A. D. 2016
CLAIM NO. 231 OF 2016
BETWEEN (DR. MARK WEIRICH CLAIMANTS (DR. ANGELA WEIRICH
(
(AND
(
(LANDTRUST LTD. DEFENDANT
BEFORE THE HONOURABLE MADAM JUSTICE MICHELLE ARANA
Mr. Nigel Ebanks of Barrow and Williams for the Applicants/Claimants
Mr. Estevan Perera of Glenn Godfrey and Co. for the Respondent/Defendant
JUDGMENT
Ors. Mark and Angela Weirich aka "the Weirichs", are husband and wife medical practitioners living in the United States of America. The Respondent/Defendant, Landtrust Ltd., is a limited liability company incorporated under Chapter 250 of the Laws of Belize engaged in real estate development with registered office at 35 New Road Belize City; it is the Developer of a condominium project known as "Sapphire Beach Resort/I. The substantive Claim arises from a Sale Agreement between the parties which the Weirichs say has been breached Landtrust Ltd. The Agreement was for the Claimants to buy and for the Defendant to sell Unit 22D at Sapphire Beach Resort, together with the exclusive rights to possession, use and enjoyment of the same for a consideration of US$310,000. The Weirichs have made two payments totaling US$93,000.00 to Landtrust Ltd. between April and June 2010. Unit 22D remains incomplete to date. The Applicants/Claimants say that under the terms of the Agreement, the unit was to be completed in an expeditious, timely and workmanlike manner and the entire project was to be done on or before December 3l5t, 2010. The Respondent/Defendant says that the Applicants/Claimants have failed to pay the balance of the purchase price, more particularly the stage payment which next falls due, resulting in the Respondent/Defendant'sfailure to perform its obligations under the Agreement. The Weirichs now seek summary judgment against Landtrust Ltd. on the grounds {i) that the Respondent/Defendant has no prospect of successfully defending the Claim; and {ii) the Respondent/Defendant has failed to put forth any viable and/or plausible defence to the Claim. The Court now decides the application.
Submissions on behalf of the Applicants/Claimants in support of the
Application for Summary Judgment
of Unit 22D is complete, and in fact only a few concrete blocks have been laid to start construction of the base of the Unit's walls. Under Clause 7.2 of the Agreement, the Respondent/Defendant was obligated to obtain strata title for the Sapphire Beach Condominium Development. By Clause 9.8 of the contract, the Respondent/Defendant was also obligated to complete construction of the entire project on or before December 3l5t, 2010. To date, almost 7 years after entering the agreement the project remains incomplete. By Clause 15e, Landtrust Ltd was obligated to complete construction of the project expeditiously and in a timely and workmanlike manner. The Weirichs say that Landtrust Ltd. has failed to fulfill all of the above obligations and in any event, the time for doing so has long since expired. Landtrust Ltd. does not deny that it has failed to complete the project and fulfill its contractual obligations; however, it says that it is the Weirichs' failure to pay the balance of the purchase price which has caused Landtrust's inability to perform its obligations under the contract. The Weirichs say that they have dutifully performed all of their obligations under the agreement and that Landtrust Ltd. has never demanded that they pay further sums. The Weirichs say that Landtrust Ltd. is admittedly in default of its obligations, and its breaches of the contract are inexcusable,and its effort to shift the blame to them is plainly an ignoble reaction to this claim in an effort to avoid liability.
"Under CPR 24.2aJ the court has the power to dispose summarily of claims and defences which have "no real prospectH of being successful. The word "rear directs the court to the need to see whether there is a realistic as opposed to a fanciful prospect of success. It is important that judges in appropriate cases should make use of the power contained in Pt. 24. In doing soJ they will give effect to the overriding objectives contained in Pt. 1. It saves expenseJ achieves expedition avoids the courtJs resources being used up on cases where that serves no purpose and is in the interest of justice. If a claimant has a case which is bound to Jan it is in his interest to know as soon as possible that that is the position. LikewiseJ if a claim is bound to succeedJ a claimant should know that as soon as possible. However; it is important that the power under Pt. 24 is kept to its proper role. It is not meant to dispense with the need for a trial where there are issues which should be investigated at trial. The properdisposal of an issue under Pt. 24 does not therefore involve the judge conducting a mini trial.H
"The principle distilled from these authorities by which a court must be guided may be stated thus: Summary Judgment should only be granted in cases where it is clear that a claim on its face obviously cannot be sustainedJ or in some other way is an abuse of the process of the court. What must be shown in the words of Lord Woolf in Swain v. Hillman is that the claim or the defence has no "rear i.e. realistic as opposed to a fanciful prospect of success. It is not required that a substantial prospect of success be shown. Nor does it mean that the claim or defence is bound to fail at trial. From this it is to be seen that the court is not tasked with adopting a sterile approach but rather to consider that matter in the context of the pleadings and such evidence as there is before it and on that basis to determine whether the claim or the defence has a real prospect of success. IL at the end of the exerciseJ the court arrives at the view that it would be difficult to see how the claimant or the defendant could establish its caseJ then it is open to the court to enter summary judgment.n
a) They entered into an Agreement;
b) They paid the consideration required of them;
d) They gave the Defendant more than ample time to perform it obligations under the Agreement;
e) When the Defendant's performance of its obligations was not forthcoming, the Claimants validly terminated the Agreement.
a) The Defendant has, as a matter of fact, committed all the breaches mentioned;b) The Defendant has not given any good reason that can lawfully justify its failure to deliver the Unit on time;
c) The Defendant's complaint that its own failure is attributable to the Claimant's breach of the Agreement has no basis in fact or law:
- The Claimants have never been required to pay and the Defendant has never demanded any further stage payment from the Claimants;
- The evidence is that several years passed before the Claimants took the positive step of seeking to have the Defendant fulfill the terms of the Agreement or otherwise the Claimants would have to terminate it in accordance with its terms;
- The Claimants so terminated the Agreement when no compliance was forthcoming;
- At the time of termination, the Defendant did not dispute the validity of the termination, nor did it say that its failure to perform was on account of Claimants' failure to pay further sums. The evidence shows that the Defendant only raises this position in response to this Claim;
- Lastly, the Defendant's obligations to complete the entire project and obtain strata title for the project are the Defendant's own obligations. The undisputed fact is that the Defendant has done neither, which cannot be
the Claimants' fault as they are but one joint purchaser in a whole scheme.
"The previous owners and Directors stole a great deal of money from the project and were imprisoned in the United States. However, this does not affect the Claimants' unit since they are to make staged payments for their construction.N
Mr. Ebanks argues that this evidence from the Defendant is the best evidence of where the Claimants' money went and why construction of the Unit has not progressed. It also evinces a crucial gap in the Defendant's failure to appreciate that it is not only responsible to complete the Unit, but it is obligated to complete the entire project. The Agreement does not simply provide for the Claimants to purchase a Unit; it entitles them to the "enjoyment, use and possession" of that Unit as a part of an entire resort development complete with all the aesthetics and amenities that such a development will have. He further contends that it is the Defendant, and not its former owners or directors, which is liable for the Claimants' loss and
liable to restore them to their previous position. The theft by the previous owners affects the Claimants gravely, as it is submitted that there is now serious reason to doubt that the project will ever be completed. Justice therefore requires that the Defendant returns the Claimants' money. All the evidence on which the parties intend to rely is already before the court. There is no reason to speculate that any further evidence would come to light later on. The case is not fit for a trial and its just disposal does not require one as the case is neither technical nor complex. Further time and costs necessary for a full trial would not be justified. The Claimants ask that the relief it seeks by this application be granted.
Submissions on behalf of The Respondent/Defendant in opposition to
Application for Summary Judgment
"Where the contractor fails to build at all or in part/ then the normal measure of damages is the cost to the employer of completing the building works in a reasonable manner less the contract price. The leading authority on the point is still Mertens v. Home Freeholds. The employer may also(though not on the facts of Mertens) recover in respect of increased costsarising through delay in completion following the contractor s failure to build.H
Mr. Perera argues that in this case, the Defendant has constructed the first stage of the condominium unit and has not constructed the second stage since it has not been paid for the second stage. He also argues that there is no section of the agreement that states that time was of the essence.
Schiffbau Und Maschinenfabrik v South India Shipping Corp [1981] 1 ALL
ER 289.
amount to a breach. If there is no express provision relating to time for payment, then payment is to be made within a reasonable time. He also argues that according to Chitty on Contracts, where one party so acts or expresses himself as to show that he does not mean to accept the obligations of the contract any further, then this may, depending on the circumstances amount to a repudiatory breach of contract. Generally, a breach of contract will only give rise to a claim for damages and the innocent party will be obliged to continue its outstanding performance of the contract notwithstanding the breach. However, where there is a breach of a condition, which amounts to a refusal to perform going to the root of the contract, then there will be a repudiatory breach, entitling the innocent party on acceptance of the repudiation, to treat the contract as at an end. It is the Defendant's position that the Claimants cannot repudiate the contract since the Claimants are not innocent parties since they refused to pay for the second stage of construction to continue, and at no point did they indicate that their failure to pay was because they required a certificate of completion. What will amount to repudiation of a contract will depend on the terms which the parties have agreed and the relative importance which they have placed on them. Unless time is of the essence,delay may amount to repudiation only where the delay gives rise to the inference that the defaulting party does not intend to be bound by the terms of the contract. Mr. Perera says that in this case, the Defendant has always respected the contract and has always stood ready willing and able to complete the construction so long as the next stage payment is received. To the contrary, a failure of the Claimants to pay the Defendant could amount to repudiation depending on the terms as to payment and the circumstances of the refusal. Since it is the very inaction of the Claimants that caused the delay, the delay should not be seen as sufficient to be considered a repudiatory breach Mayhaven Healthcare ltd. v. Bothma & Bothma {2009) EWHC 2634.
states that the contract would be governed by the Laws of Belize. The cost of taking technical and legal advice in the preparation of a claim was held not to be recoverable as damages in Johnston v. W. H. Brown Construction (Dundee) ltd. [2000] ScotCS 94; [2000] BLR 243. The application for summary judgment should be dismissed, and the matter should be allowed to proceed to a full trial.
Submissions in Reply in support of Application for Summary Judgment
lawfully require payment from another contracting party Civil Appeal No. 14 of 2016 Bella Vista Development ltd. and anor. v. /mer Hernandez Development Co. ltd. (Del. March 24th, 2017)
29/04/2016. The Respondent did not reject the Applicants' termination of the Agreement in 2014, and only raises the allegation of breach by the Applicants in response to this Claim. The Applicants stress that the Respondent does not dispute that it has failed to perform the Agreement.
Decision
[Context"4.2 The stages of construction identified in clauses 4.1.lJ 4.1.2.J 4.1.3 and 4.1.4. shall be deemed completed upon the issue of a stage completion certificate signed by the designer or engineer supervising the construction of Sapphire Beach Resort EastJ such person to be selected and engaged by the Vendor in its sole discretion.H
There has been no compliance by the Respondent with the requirement that a Stage Completion Certificate be presented to the Applicants before further payment is made. Contrary to the position taken by Learned Counsel Mr. Perera in his oral arguments before this court, such a certificate is not an insignificant little piece of paper. That is the document which both parties have agreed will determine when and how and on what basis, payments under the contract will be made. That document certifies (thru the designer or engineer) that a certain stage of this building has been completed and therefore the next stage payment is due and I agree with Mr. Ebanks' characterization of the certificate of completion as a necessary pre-condition for further payment to be made under the terms of the contract. I also fully agree with the position of Mr. Ebanks that the
Applicants were entitled to terminate the contract due to the Respondent's non-performance of its obligations, as that non-performance clearly amounted to a breach. I must also say that I find little merit in Mr. Perera's arguments that the contract did not require time to be of the essence. A perusal of the contract reveals that Clause 9.8 stated that the Respondent was to "make all reasonable effort to ensure that construction of all buildings with adjoining swimming pools of the condominium project was to be completed by December 2010/1. The contract was signed by the parties on April 21st, 2010, so clearly, time was of the essence. Further clauses such as Clause lS{e) headed "Warranties" requires that "the Vendor shall use all due diligence to complete construction of the condominium project expeditiously and in a timely and workmanlike manner/I. I am further buttressed in my view that this application for summary judgment should succeed, by the evidence from the Defendant itself, where its Director Ms. Joy Reed has sworn to an affidavit expressly stating that the Landtrust Ltd.'s previous owners swindled considerable sums of money from the Defendant company and they are presently incarcerated in the United States. I find that the Applicants have been extremely patient with the Respondent in all the circumstances and they are entitled to the relief
which they seek. The Defence is not likely to succeed, and in these circumstances there is no point in expending further time and resources in a full trial. The Defence is struck out, and summary judgment is ordered in favour of the Applicants/Claimants. Prescribed costs awarded to the Applicants/Claimants to be paid by the Respondent/Defendant for this application and for the substantive claim as set out in the Civil Procedure Rules. I also find the costs of the US attorneys requested by the Claimants to be reasonable in these circumstances as part of pre-litigation costs and the court so orders.
Dated this Friday, 1st day of December, 2017
Michelle Arana Supreme Court Judge